title: Discharging the BGP condition
description: How to process the discharge of the deemed Biodiversity Gain Plan condition in Mycelia.
---

[Skip to content](https://support.verna.earth/mycelia-support/discharging-the-bgp-condition#main-content)

[![Verna-logo-dark](https://support.verna.earth/hs-fs/hubfs/Verna-logo-dark.png?width=200&height=47&name=Verna-logo-dark.png)](https://verna.earth/)

Open main navigation

Close main navigation

- [Contact us](mailto:mycelia-support@verna.earth)

[Contact us](mailto:mycelia-support@verna.earth)

 How can we help you?

- There are no suggestions because the search field is empty.

1. [Mycelia support](https://support.verna.earth/mycelia-support?hsLang=en-gb)
2. [Discharge of condition](https://support.verna.earth/mycelia-support/discharge-of-condition?hsLang=en-gb)

# Discharging the BGP condition

## How to process the discharge of the deemed Biodiversity Gain Plan condition in Mycelia.

[← Previous: Discharge of condition: an overview](https://support.verna.earth/mycelia-support/discharge-of-condition-overview?hsLang=en-gb)

---

**Who this is for:** Validation officers, planning officers and ecologists.

**On this page**

- [1. Validate a Biodiversity Gain Plan at discharge of condition](https://support.verna.earth/mycelia-support/discharging-the-bgp-condition#validate-a-biodiversity-gain-plan-at-discharge-of-condition)
- [2. Record BGP approval](https://support.verna.earth/mycelia-support/discharging-the-bgp-condition#record-bgp-approval)

## 1. Validate a Biodiversity Gain Plan at discharge of condition

> **Before you start:** This is for the deemed BGP discharge condition only (see the overview). Process any other conditions separately.

### What to do

1. 1\. In Mycelia, search for the main planning application reference and open the existing case.
2. 2\. Before uploading anything, note the baseline from the previously approved metric: open the Overview tab, go to the Metric Summary, and note the on-site baseline area and biodiversity unit (BU) values.
3. 3\. Add the discharge of condition reference as a new case code.
4. 4\. Drag and drop the new submission documents into the existing case. The new metric is promoted and read by Mycelia automatically.
5. 5\. Re-run validation on the new metric: check the new Metric Summary on-site baseline matches the values you noted, then review the national and local validation results as usual.
6. 6\. Update the case status (for example “BGP submitted”), complete the discharge process in your planning system, and hand over to the Case Officer.

> **Important:** The baseline must not change between the original approval and the BGP discharge – the new metric’s on-site values should match the previously approved metric. If they don’t, or the metric is invalid, request a revised metric before proceeding.

## 2. Record BGP approval

Once the Biodiversity Gain Plan is approved, record it on the case so the approval is captured and the case feeds the biodiversity duty report correctly.

### What to do

1. 1\. Open the case overview.
2. 2\. Set the Biodiversity Gain Plan status to “Approved” and enter the approval date.
3. 3\. Update the case status to reflect approval (for example “BGP approved”).

> **Important:** If the BGP status and date aren’t logged here, the case won’t be reporting-ready – this is the field the biodiversity duty report relies on. See “ [Generate the Biodiversity Duty report](https://support.verna.earth/mycelia-support/generate-the-biodiversity-duty-report?hsLang=en-gb)”.

---

[← Previous: Discharge of condition: an overview](https://support.verna.earth/mycelia-support/discharge-of-condition-overview?hsLang=en-gb)

- [Getting started](https://support.verna.earth/mycelia-support/getting-started?hsLang=en-gb)
- [About BNG & Mycelia](https://support.verna.earth/mycelia-support/about-bng-mycelia?hsLang=en-gb)
- [Working with cases](https://support.verna.earth/mycelia-support/working-with-cases?hsLang=en-gb)
- [Validation](https://support.verna.earth/mycelia-support/validation?hsLang=en-gb)
- [Assessment & determination](https://support.verna.earth/mycelia-support/assessment-determination?hsLang=en-gb)
- [Discharge of condition](https://support.verna.earth/mycelia-support/discharge-of-condition?hsLang=en-gb)
- [Monitoring](https://support.verna.earth/mycelia-support/monitoring?hsLang=en-gb)
- [Reporting](https://support.verna.earth/mycelia-support/reporting?hsLang=en-gb)
- [Managing your organisation](https://support.verna.earth/mycelia-support/managing-your-organisation?hsLang=en-gb)

[![Verna-logo-light](https://support.verna.earth/hs-fs/hubfs/Verna-logo-light.png?width=150&height=35&name=Verna-logo-light.png "Verna-logo-light")](https://s47820.pcdn.co/wp-content/uploads/verna-logo.png.webp)

© 2026 Verna Earth Solutions Ltd.

Company number: 12745191